Search

Milestone Marked at Kentucky Chemical Weapons Destruction Plant

Milestone Marked at Kentucky Chemical Weapons Destruction Plant

Destruction of GB projectiles moves U.S. closer to eliminating its chemical weapons

PR Newswire

RESTON, Va., May 12, 2020 /PRNewswire/ — A Bechtel-led team has successfully completed the destruction of projectiles containing the nerve agent GB at a chemical weapons facility in Kentucky.


Two operators place one of the last overpacked 8-inch projectiles containing the GB nerve agent into a tray to begin the destruction process at the Blue Grass Chemical Agent-Destruction Pilot Plant in Kentucky. The final 8-inch projectile of GB was destroyed on May 11, marking the complete elimination of an entire type of chemical weapon.

The destruction of the nearly 4,000 GB projectiles at the Blue Grass Chemical Agent-Destruction Pilot Plant (BGCAPP) moves the U.S. one step closer to meeting an international treaty obligation to eliminate the country’s stockpile of chemical weapons.

Destruction of the GB projectiles began in January and continued safely while the COVID-19 pandemic has impacted the country.

“The nation determined early on that the eradication of chemical weapons is an essential mission,” said Barbara Rusinko, president of Bechtel’s Nuclear, Security & Environmental business unit. “The team at the plant quickly adapted to the new ways of working, did so safely, and delivered on this phase of the mission. My thanks and appreciation go out to our team and our customers in the Department of Defense.”

Approximately 523 tons of chemical agents were originally stored in weapons at the Blue Grass Army Depot near Richmond, Kentucky. Destruction of projectiles containing the blister agent mustard began last June. Together, more than 61 tons of GB and mustard agent have been safely destroyed at the Blue Grass facility.

There were no recordable injuries during the GB projectile campaign.

“The performance of the Blue Grass team can only be described as excellent,” said Ron Hink, Bechtel Parsons Blue Grass project manager. “While this is only the first of four nerve agent campaigns, we clearly demonstrated our commitment to safety, compliance and adherence to proven procedures.”

Automated equipment disassembled and drained the GB from the weapons. The agent was neutralized and will be broken down into carbon dioxide, water and salts in a secondary process. The metal parts were heated to more than 1,000 degrees Fahrenheit for decontamination and then safely recycled.

Also slated to be destroyed at the facility are projectiles containing the nerve agent VX, and rockets containing both GB and VX. Destruction of all chemical weapons stored at the depot is scheduled to be completed by Dec. 31, 2023.

BGCAPP was built and is being operated under contract to the Department of Defense’s Program Executive Office, Assembled Chemical Weapons Alternatives. Bechtel Parsons Blue Grass is a joint venture of Bechtel National Inc. and Parsons Government Services Inc.

Historic commitment to global security

Since the 1980s, Bechtel has had an active role in U.S. and international efforts to eliminate chemical weapons. With the destruction of the stockpiles underway in Colorado and Kentucky, along with previous projects in Alabama and Maryland, Bechtel will have safely eliminated nearly 5,000 tons of chemical weapons in rockets, artillery rounds, mortar shells, and storage canisters at four of the nine original U.S. storage depots.

Learn more:

About Bechtel:

Bechtel is a trusted engineering, construction and project management partner to industry and government. Differentiated by the quality of our people and our relentless drive to deliver the most successful outcomes, we align our capabilities to our customers’ objectives to create a lasting positive impact. Since 1898, we have helped customers complete more than 25,000 projects in 160 countries on all seven continents that have created jobs, grown economies, improved the resiliency of the world’s infrastructure, increased access to energy, resources, and vital services, and made the world a safer, cleaner place. 

Bechtel serves the Infrastructure; Nuclear, Security & Environmental; Oil, Gas & Chemicals; and Mining & Metals markets. Our services span from initial planning and investment, through start-up and operations.  www.Bechtel.com  

Contact:
Fred deSousa
tfdesous@Bechtel.com  
Office: 703.429.6435
Mobile: 571.364-5733

Cision View original content to download multimedia:http://www.prnewswire.com/news-releases/milestone-marked-at-kentucky-chemical-weapons-destruction-plant-301058069.html

SOURCE Bechtel

Congress Updates

Senate Appropriators Press On Supplemental’s Requests Beyond Iran Scope, Hegseth Urges Full Funding

Senate appropriators have pressed Pentagon leadership on the decision to include funds in the Iran war supplemental request for items beyond the current military operation, while Defense Secretary Pete Hegseth […]


House Republicans’ Blueprint For Reconciliation 3.0 Includes $60 Billion For Defense

House Republicans on Wednesday unveiled a blueprint for a third reconciliation bill that includes $60 billion for defense, a figure slightly below the Trump administration’s request to cover Iran war […]


Senate Dems Block Consideration Of FY ‘27 NDAA Over Iran War Concerns

Senate Democrats on Tuesday blocked a vote to advance consideration of the chamber’s $1.14 trillion fiscal year 2027 National Defense Authorization (NDAA). The procedural vote was 46-50, failing to reach […]


Concerns Raised At SASC Hearing On Unobligated Reconciliation Funds And Lack Of Updates On Iran War Cost

Members of the Senate Armed Services Committee (SASC) raised concerns at a hearing on Tuesday about the majority of funds in the $153 billion first reconciliation bill being unobligated thus […]