Yearlong CR Would Force Air Force to Break KC-46A Contract with Boeing

NATIONAL HARBOR, Md. —The Air Force has set Sept. 25 as the new first flight date for its KC-46A refueling tanker, but a long-term Continuing Resolution (CR) could spell more trouble for the program, its program executive officer said on Tuesday.

Artist rendering of a KC-46A refueling F-35 fighters. Rendering by Boeing
Artist rendering of a KC-46A refueling F-35 fighters. Rendering by Boeing

Under the current schedule, the KC-46A program will hit a Milestone C decision in April 2016, after which it is scheduled to award contracts to Boeing [BA] for the first two lots of low-rate initial production aircraft, said Air Force Brig. Gen. Duke Richardson, program executive officer for tankers.

“LRIP Lot 2 is fiscal year 2016 funding, so if we get into a CR situation, it will create a very large problem for this program” in that it will not be able to award a contract as planned for 12 aircraft, he said during a speech at the Air Force Association’s Air and Space Conference. 

Under the terms of its contract, the Air Force could buy anywhere from eight to 11 aircraft during LRIP Lot 2 and pay a penalty to Boeing. However, buying fewer than eight aircraft would result in the contract being broken, and a yearlong CR would only allow for the purchase of seven aircraft, he told reporters after the briefing.

“This contract that we have is a very nice contract in a lot of ways, but it’s also fairly stringent in terms of what it requires of the government,” he said. “It requires funding stability and requirements stability. Up to this point we have delivered both.”

Throughout his speech, Richardson stated that the service is struggling keeping the program on schedule, not with the performance of the aircraft.

Under the current contract, Boeing is required to deliver the first 18 tankers by August 2017. Richardson said he was “cautiously confident” that the company would meet the “required assets available” deadline, but noted that technical issues have eaten away all of the slack built into the schedule.

The service is preparing the first fully equipped KC-46A aircraft, called EMD2, for its inaugural flight on Sept. 25, he said. The flight was originally scheduled for April, but problems—including a recent fuel contamination issue—pushed back that date.

Aerial refueling demonstrations are scheduled to begin early next year.



Congress Updates

Industry Groups ‘Urge’ Congress To Block Stock Buyback Restriction From Final FY ‘27 NDAA

More than three dozen industry associations on Monday called on congressional defense committee leaders to scrap a provision in the final version of the next National Defense Authorization Act that […]


Senior GOP HASC Members Wittman, Turner Ousted Amid Dems’ Blue Wave

Two senior Republicans on the House Armed Services Committee, including a potential frontrunner for the panel’s top GOP role, have officially lost their reelection bids. Reps. Rob Wittman (R-Va.) and […]


Dems’ Big Night Set To Reshape Top Defense Committee Spots, As Key GOP’ers Knocked Off

Democrats’ sweeping victories in Tuesday’s midterms, taking back control of the House and Senate, are set to reshape key spots atop defense committees, to include House Armed Services panels and […]


Key Defense Committee Members Face Tight Midterm Races, Including HASC GOP’ers In Virginia

As the mid-term elections near with polls showing an increasing likelihood of a switch in majority control in the House and potentially the Senate, three Virginia Republicans on the House […]