The National Nuclear Security Administration (NNSA) planned to have a detailed cost and schedule estimate for producing new nuclear weapon cores for the first time since the Cold War by Sept. 30, 2025, according to a Government Accountability Office report released Thursday. That’s the date by which the agency planned to advance its two planned plutonium pit factories to the project management milestone known as Critical Decision 2: the usual time for establishing a cost and schedule baseline for big…